IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

6,996

matching recommendations
Reset
ARC 2.3 Electrical Power
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD0299 # 04 Y:1989 04 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $889 $750 Implemented
UD0300 # 01 Y:1989 01 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $3,966 $0 Not Implemented
UD0300 # 02 Y:1989 02 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $3,322 $0 Not Implemented
UD0301 # 01 Y:1990 01 1990 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,313 $0 Not Implemented
UD0301 # 02 Y:1990 02 1990 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $9,236 $0 Not Implemented
UD0301 # 03 Y:1990 03 1990 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $8,636 $0 Not Implemented
UD0301 # 04 Y:1990 04 1990 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $7,480 $0 Not Implemented
WI0063 # 01 Y:1989 01 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $10,384 $0 Implemented
WI0063 # 05 Y:1989 05 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,658 $4,000 Implemented
WI0064 # 01 Y:1989 01 1989 BURN FOSSIL FUEL TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR AND USE STEAM EXHAUST FOR HEAT $98,647 $400,000 Not Implemented
OR0061 # 03 Y:1989 03 1989 OPTIMIZE PLANT POWER FACTOR $4,155 $2,000 Implemented
OR0062 # 08 Y:1989 08 1989 OPTIMIZE PLANT POWER FACTOR $5,423 $11,400 Not Implemented
OR0063 # 07 Y:1989 07 1989 OPTIMIZE PLANT POWER FACTOR $5,520 $6,300 Not Implemented
OR0064 # 05 Y:1989 05 1989 OPTIMIZE PLANT POWER FACTOR $1,704 $975 Implemented
MA0157 # 03 Y:1989 03 1989 DE-ENERGIZE EXCESS TRANSFORMER CAPACITY $545 $584 Not Implemented
GT0383 # 01 Y:1989 01 1989 USE DEMAND CONTROLLER OR LOAD SHEDDER $17,960 $20,000 Implemented
KU0292 # 06 Y:1989 06 1989 USE DEMAND CONTROLLER OR LOAD SHEDDER $2,284 $3,144 Not Implemented
UD0298 # 02 Y:1989 02 1989 USE DEMAND CONTROLLER OR LOAD SHEDDER $1,921 $1,500 Not Implemented
UD0296 # 02 Y:1989 02 1989 USE DEMAND CONTROLLER OR LOAD SHEDDER $2,200 $2,000 Not Implemented
AM0070 # 02 Y:1989 02 1989 OPTIMIZE PLANT POWER FACTOR $3,500 $4,000 Not Implemented
OR0058 # 02 Y:1989 02 1989 USE DEMAND CONTROLLER OR LOAD SHEDDER $2,976 $200 Implemented
OR0058 # 03 Y:1989 03 1989 USE DEMAND CONTROLLER OR LOAD SHEDDER $1,940 $200 Not Implemented
WI0061 # 01 Y:1989 01 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $15,484 $0 Not Implemented
WI0062 # 04 Y:1989 04 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $3,647 $0 Not Implemented
WI0061 # 03 Y:1989 03 1989 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $4,969 $0 Implemented