Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
6,709
matching recommendationsARC | 4. | DIRECT PRODUCTIVITY ENHANCEMENTS |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0620 # 04 Y:2013 | 04 | 2013 | MODIFY STARTUP/SHUTDOWN TIMES | $442 | $481 | Not Implemented |
SU0349 # 01 Y:2013 | 01 | 2013 | PAY BILLS ON TIME TO AVOID LATE FEES | $6,610 | $0 | Implemented |
NC0496 # 09 Y:2013 | 09 | 2013 | OPTIMIZE LOT SIZES TO REDUCE INVENTORY CARRYING COSTS | $65,547 | $10,000 | Implemented |
NC0496 # 10 Y:2013 | 10 | 2013 | CONDENSE OPERATION INTO ONE BUILDING | $37,518 | $5,000 | Implemented |
WM0031 # 09 Y:2013 | 09 | 2013 | IMPROVE SPACE COMFORT CONDITIONING | $3,840 | $1,500 | Not Implemented |
WM0031 # 07 Y:2013 | 07 | 2013 | PAY BILLS ON TIME TO AVOID LATE FEES | $593 | $0 | Implemented |
OR0618 # 02 Y:2013 | 02 | 2013 | MODIFY STARTUP/SHUTDOWN TIMES | $10,380 | $800 | Not Implemented |
MI0248 # 07 Y:2013 | 07 | 2013 | PAY BILLS ON TIME TO AVOID LATE FEES | $1,005 | $240 | Implemented |
OR0615 # 01 Y:2013 | 01 | 2013 | ELIMINATE SHUTDOWNS OF CONTROLS DUE TO OVERHEATING | $24,283 | $1,000 | Implemented |
OR0616 # 01 Y:2013 | 01 | 2013 | INSTALL SENSORS TO DETECT DEFECTS | $145,630 | $200 | Implemented |
OR0615 # 03 Y:2013 | 03 | 2013 | ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS | $791,616 | $300,000 | Not Implemented |
WM0030 # 07 Y:2013 | 07 | 2013 | MODIFY STARTUP/SHUTDOWN TIMES | $3,034 | $0 | Not Implemented |
SU0350 # 03 Y:2013 | 03 | 2013 | PAY BILLS ON TIME TO AVOID LATE FEES | $1,239 | $0 | Implemented |
MI0246 # 08 Y:2013 | 08 | 2013 | PAY BILLS ON TIME TO AVOID LATE FEES | $945 | $240 | Implemented |
IP0018 # 01 Y:2013 | 01 | 2013 | APPLY FOR INVESTMENT INCENTIVES | $42,227 | $0 | Not Implemented |
BD0431 # 07 Y:2013 | 07 | 2013 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $12,000 | $1,000 | Implemented |
NC0493 # 13 Y:2013 | 13 | 2013 | CONDENSE OPERATION INTO ONE BUILDING | $21,473 | $10,000 | Implemented |
TT0109 # 06 Y:2013 | 06 | 2013 | APPLY FOR INVESTMENT INCENTIVES | $2,271 | $0 | Implemented |
OR0610 # 03 Y:2013 | 03 | 2013 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $161,127 | $238,200 | Not Implemented |
CO0671 # 01 Y:2013 | 01 | 2013 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $62,960 | $65,530 | Implemented |
WM0027 # 07 Y:2013 | 07 | 2013 | MODIFY WORKLOAD | $53,406 | $0 | Not Implemented |
WM0027 # 09 Y:2013 | 09 | 2013 | AUTOMATE FINISHING PROCESS | $53,406 | $11,000 | Not Implemented |
BD0430 # 07 Y:2013 | 07 | 2013 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $4,500 | $10,000 | Implemented |
OR0608 # 01 Y:2013 | 01 | 2013 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $32,340 | $0 | Implemented |
OR0608 # 02 Y:2013 | 02 | 2013 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $107,138 | $55,641 | Implemented |