Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,719
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0604 # 05 Y:2013 | 05 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $11,228 | $11,850 | Implemented |
OR0602 # 01 Y:2013 | 01 | 2013 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $199,441 | $59,312 | Implemented |
OR0602 # 03 Y:2013 | 03 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $14,855 | $19,467 | Implemented |
OR0602 # 04 Y:2013 | 04 | 2013 | INSTALL OCCUPANCY SENSORS | $5,434 | $10,283 | Implemented |
OR0602 # 06 Y:2013 | 06 | 2013 | OPTIMIZE PLANT POWER FACTOR | $3,822 | $9,150 | Implemented |
OR0602 # 08 Y:2013 | 08 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,435 | $3,004 | Implemented |
OR0600 # 02 Y:2012 | 02 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,704 | $500 | Implemented |
OR0600 # 03 Y:2012 | 03 | 2012 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $334 | $0 | Implemented |
OR0600 # 04 Y:2012 | 04 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $940 | $392 | Implemented |
OR0600 # 06 Y:2012 | 06 | 2012 | ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF | $6,653 | $385 | Implemented |
OR0600 # 07 Y:2012 | 07 | 2012 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,399 | $560 | Implemented |
OR0600 # 08 Y:2012 | 08 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,835 | $2,724 | Implemented |
OR0599 # 01 Y:2012 | 01 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,611 | $12,467 | Implemented |
OR0599 # 02 Y:2012 | 02 | 2012 | INSTALL AUTOMATIC PACKING EQUIPMENT | $35,308 | $0 | Implemented |
OR0599 # 04 Y:2012 | 04 | 2012 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $1,409 | $0 | Implemented |
OR0594 # 03 Y:2012 | 03 | 2012 | Install Anaerobic Digester | $1,369,423 | $3,468,069 | Implemented |
OR0594 # 04 Y:2012 | 04 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,684 | $7,360 | Implemented |
OR0591 # 01 Y:2012 | 01 | 2012 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $920,649 | $25,909 | Implemented |
OR0591 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,274 | $6,968 | Implemented |
OR0590 # 02 Y:2012 | 02 | 2012 | USE OPTIMUM TEMPERATURE | $3,137 | $0 | Implemented |
OR0589 # 02 Y:2012 | 02 | 2012 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,711 | $6,200 | Implemented |
OR0589 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,823 | $53,151 | Implemented |
OR0585 # 04 Y:2012 | 04 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,028 | $2,305 | Implemented |
OR0585 # 11 Y:2012 | 11 | 2012 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $12,086 | $16,390 | Implemented |
OR0583 # 01 Y:2012 | 01 | 2012 | AVOID FROST FORMATION ON EVAPORATORS | $3,140 | $2,412 | Implemented |