Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,732
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0644 # 06 Y:2015 | 06 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,865 | $3,865 | Implemented |
OR0643 # 01 Y:2015 | 01 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,697 | $0 | Implemented |
OR0643 # 02 Y:2015 | 02 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,403 | $46,360 | Implemented |
OR0642 # 01 Y:2015 | 01 | 2015 | MODIFY STARTUP/SHUTDOWN TIMES | $6,091 | $44,052 | Implemented |
OR0642 # 02 Y:2015 | 02 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,013 | $24,232 | Implemented |
OR0642 # 05 Y:2015 | 05 | 2015 | ADJUST BURNERS FOR EFFICIENT OPERATION | $1,833 | $500 | Implemented |
OR0642 # 07 Y:2015 | 07 | 2015 | INSULATE BARE EQUIPMENT | $898 | $2,015 | Implemented |
OR0641 # 01 Y:2014 | 01 | 2014 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $17,076 | $2,794 | Implemented |
OR0641 # 02 Y:2014 | 02 | 2014 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $13,580 | $8,760 | Implemented |
OR0641 # 04 Y:2014 | 04 | 2014 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $1,470 | $1,577 | Implemented |
OR0641 # 05 Y:2014 | 05 | 2014 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $581 | $1,121 | Implemented |
OR0640 # 01 Y:2014 | 01 | 2014 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $131,605 | $242,261 | Implemented |
OR0640 # 05 Y:2014 | 05 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,092 | $12,092 | Implemented |
OR0639 # 01 Y:2014 | 01 | 2014 | IMPROVE COMBUSTION CONTROL CAPABILITY | $14,677 | $12,315 | Implemented |
OR0639 # 02 Y:2014 | 02 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,461 | $360 | Implemented |
OR0639 # 04 Y:2014 | 04 | 2014 | INSULATE BARE EQUIPMENT | $7,377 | $7,643 | Implemented |
OR0638 # 04 Y:2014 | 04 | 2014 | MINIMIZE WATER USAGE | $1,003 | $0 | Implemented |
OR0638 # 07 Y:2014 | 07 | 2014 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $21,180 | $10,000 | Implemented |
OR0636 # 03 Y:2014 | 03 | 2014 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $5,708 | $7,000 | Implemented |
OR0632 # 02 Y:2014 | 02 | 2014 | INSTALL OCCUPANCY SENSORS | $2,497 | $2,837 | Implemented |
OR0632 # 04 Y:2014 | 04 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $870 | $500 | Implemented |
OR0628 # 07 Y:2014 | 07 | 2014 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $9,718 | $2,460 | Implemented |
OR0617 # 01 Y:2013 | 01 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $20,239 | $20,000 | Implemented |
OR0617 # 02 Y:2013 | 02 | 2013 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $10,455 | $4,610 | Implemented |
OR0617 # 03 Y:2013 | 03 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $21,219 | $131,114 | Implemented |