Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
6,845
matching recommendationsARC | 2.3 | Electrical Power |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1109 # 07 Y:2024 | 07 | 2024 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $8,413 | $3,850 | n/a |
AS0571 # 06 Y:2024 | 06 | 2024 | USE POWER DURING OFF-PEAK PERIODS | $492 | $511 | Implemented |
UF0612 # 02 Y:2024 | 02 | 2024 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $55,068 | $30,945 | n/a |
SU0550 # 01 Y:2024 | 01 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $2,161 | $0 | n/a |
NT0021 # 02 Y:2024 | 02 | 2024 | OPTIMIZE PLANT POWER FACTOR | $19,175 | $6,411 | n/a |
UL2403 # 02 Y:2024 | 02 | 2024 | OPTIMIZE PLANT POWER FACTOR | $32,359 | $12,025 | n/a |
UF0611 # 06 Y:2024 | 06 | 2024 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $5,901 | $7,320 | n/a |
UF0611 # 01 Y:2024 | 01 | 2024 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $99,213 | $111,120 | n/a |
UD1081 # 09 Y:2024 | 09 | 2024 | OPTIMIZE PLANT POWER FACTOR | $6,380 | $17,600 | n/a |
SU0549 # 02 Y:2024 | 02 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $7,711 | $0 | n/a |
UW2404 # 01 Y:2024 | 01 | 2024 | OPTIMIZE PLANT POWER FACTOR | $141,402 | $150,381 | n/a |
UF0610 # 02 Y:2024 | 02 | 2024 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $28,883 | $18,333 | n/a |
SD0651 # 05 Y:2024 | 05 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $21,799 | $0 | n/a |
SU0548 # 04 Y:2024 | 04 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $4,285 | $0 | n/a |
SD0653 # 02 Y:2024 | 02 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $91,923 | $0 | n/a |
AS0573 # 01 Y:2024 | 01 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $67,584 | $135,000 | Not Implemented |
SD0652 # 03 Y:2024 | 03 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $142,534 | $0 | n/a |
UC2402 # 02 Y:2024 | 02 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $7,849 | $31,027 | n/a |
UC2402 # 09 Y:2024 | 09 | 2024 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $6,701 | $64,088 | n/a |
SF0616 # 03 Y:2024 | 03 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $551 | $550 | n/a |
CI0029 # 02 Y:2024 | 02 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $127,600 | $20,500 | n/a |
IP0188 # 02 Y:2024 | 02 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $27,927 | $2,500 | Not Implemented |
AM0908 # 05 Y:2024 | 05 | 2024 | OPTIMIZE PLANT POWER FACTOR | $47,600 | $59,770 | n/a |
AM0908 # 01 Y:2024 | 01 | 2024 | BURN FOSSIL FUEL TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR AND USE STEAM EXHAUST FOR HEAT | $210,130 | $2,300,000 | n/a |
UL2401 # 03 Y:2024 | 03 | 2024 | OPTIMIZE PLANT POWER FACTOR | $17,320 | $13,000 | n/a |