Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
6,717
matching recommendationsARC | 4. | DIRECT PRODUCTIVITY ENHANCEMENTS |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0241 # 07 Y:2000 | 07 | 2000 | REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | $31,500 | $20,000 | Not Implemented |
AS0275 # 07 Y:2000 | 07 | 2000 | ELIMINATE SHIFT | $52,500 | $16,000 | Not Implemented |
HO0227 # 22 Y:2000 | 22 | 2000 | EXPAND OPERATIONS INTO UNUSED SPACE | $153,465 | $300,000 | Not Implemented |
HO0227 # 13 Y:2000 | 13 | 2000 | IMPROVE SPACE COMFORT CONDITIONING | $1,560 | $600 | Implemented |
HO0227 # 20 Y:2000 | 20 | 2000 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $1,440 | $968 | Not Implemented |
HO0227 # 21 Y:2000 | 21 | 2000 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $2,000 | $250 | Implemented |
HO0227 # 14 Y:2000 | 14 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $20,800 | $5,000 | Not Implemented |
HO0227 # 15 Y:2000 | 15 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $4,666 | $500 | Not Implemented |
HO0227 # 16 Y:2000 | 16 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $39,375 | $500 | Not Implemented |
HO0227 # 17 Y:2000 | 17 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $6,240 | $500 | Implemented |
HO0227 # 18 Y:2000 | 18 | 2000 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $32,340 | $0 | Implemented |
HO0227 # 19 Y:2000 | 19 | 2000 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $6,836 | $600 | Not Implemented |
GT0685 # 07 Y:2000 | 07 | 2000 | INSTALL AUTOMATIC PACKING EQUIPMENT | $144,500 | $150,000 | Not Implemented |
GT0685 # 06 Y:2000 | 06 | 2000 | INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM | $93,536 | $30,000 | Not Implemented |
AM0368 # 14 Y:2000 | 14 | 2000 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $8,800 | $0 | Not Implemented |
CO0460 # 08 Y:2000 | 08 | 2000 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $166,400 | $40,000 | Implemented |
CO0460 # 09 Y:2000 | 09 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $72,730 | $122,000 | Implemented |
AM0368 # 05 Y:2000 | 05 | 2000 | PURCHASE EQUIPMENT INSTEAD OF LEASING | $131,000 | $317,000 | Not Implemented |
TP0014 # 02 Y:2000 | 02 | 2000 | ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS | $3,047 | $96 | Not Implemented |
AS0274 # 11 Y:2000 | 11 | 2000 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $54,284 | $180,000 | Not Implemented |
AS0274 # 12 Y:2000 | 12 | 2000 | APPLY FOR INVESTMENT INCENTIVES | $1,580 | $60 | Not Implemented |
TN0676 # 02 Y:2000 | 02 | 2000 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $37,314 | $28,050 | Not Implemented |
TN0676 # 01 Y:2000 | 01 | 2000 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $105,000 | $94,080 | Not Implemented |
DS0160 # 08 Y:2000 | 08 | 2000 | INSTALL SYSTEM TO COLLECT SCRAP | $433 | $100 | Not Implemented |
DS0160 # 07 Y:2000 | 07 | 2000 | INSTALL AUTOMATIC PACKING EQUIPMENT | $82,554 | $70,000 | Not Implemented |