Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
806
matching recommendationsARC | 4. | DIRECT PRODUCTIVITY ENHANCEMENTS |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0241 # 07 Y:2000 | 07 | 2000 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $12,880 | $9,000 | Implemented |
UF0241 # 06 Y:2000 | 06 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $1,741,926 | $6,200,000 | Not Implemented |
UF0242 # 08 Y:2000 | 08 | 2000 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $12,880 | $9,000 | Implemented |
UF0241 # 03 Y:2000 | 03 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $122,360 | $141,700 | Not Implemented |
UF0242 # 07 Y:2000 | 07 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $1,741,926 | $6,200,000 | Not Implemented |
UF0242 # 03 Y:2000 | 03 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $122,360 | $141,700 | Not Implemented |
OK0605 # 07 Y:2000 | 07 | 2000 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $5,473,600 | $4,750,000 | Not Implemented |
OK0605 # 08 Y:2000 | 08 | 2000 | MODIFY WORKLOAD | $958,400 | $500,000 | Not Implemented |
OK0605 # 04 Y:2000 | 04 | 2000 | MODIFY WORKLOAD | $1,214,000 | $850,000 | Not Implemented |
OK0605 # 06 Y:2000 | 06 | 2000 | PURCHASE MATERIAL FROM SUPPLIER IN CUSTOMIZED PACKAGING | $528,240 | $500,000 | Not Implemented |
OK0605 # 05 Y:2000 | 05 | 2000 | INSTALL AUTOMATIC PACKING EQUIPMENT | $232,800 | $280,000 | Not Implemented |
UF0264 # 11 Y:2000 | 11 | 2000 | PAY BILLS ON TIME TO AVOID LATE FEES | $4,784 | $0 | Implemented |
AR0197 # 08 Y:2000 | 08 | 2000 | MAINTAIN/ENLARGE A STOCK OF SPARE PARTS | $80,371 | $16,150 | Not Implemented |
CO0479 # 06 Y:2000 | 06 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $179,700 | $0 | Not Implemented |
OK0608 # 05 Y:2000 | 05 | 2000 | PAY BILLS ON TIME TO AVOID LATE FEES | $14,152 | $0 | Implemented |
CO0478 # 09 Y:2000 | 09 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $6,350 | $12,000 | Implemented |
UF0265 # 12 Y:2000 | 12 | 2000 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $9,648 | $0 | Implemented |
MA0478 # 08 Y:2000 | 08 | 2000 | PAY BILLS ON TIME TO AVOID LATE FEES | $1,244 | $0 | Not Implemented |
MA0478 # 02 Y:2000 | 02 | 2000 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $9,000 | $40,000 | Not Implemented |
MS0173 # 11 Y:2000 | 11 | 2000 | PAY BILLS ON TIME TO AVOID LATE FEES | $1,514 | $50 | Not Implemented |
GT0705 # 08 Y:2000 | 08 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $120,000 | $700,000 | Not Implemented |
ME0305 # 06 Y:2000 | 06 | 2000 | AUTOMATE FINISHING PROCESS | $15,000 | $41,800 | Implemented |
OK0606 # 01 Y:2000 | 01 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $59,500 | $115,187 | Not Implemented |
AR0195 # 06 Y:2000 | 06 | 2000 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $279,468 | $10,335 | n/a |
OK0607 # 02 Y:2000 | 02 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $43,000 | $70,000 | Not Implemented |