Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
47
matching recommendationsARC | 4. | DIRECT PRODUCTIVITY ENHANCEMENTS |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0696 # 02 Y:2015 | 02 | 2015 | MODIFY WORKLOAD | $8,280 | $0 | Not Implemented |
SU0401 # 01 Y:2015 | 01 | 2015 | PAY BILLS ON TIME TO AVOID LATE FEES | $2,820 | $0 | Implemented |
IP0054 # 02 Y:2015 | 02 | 2015 | PAY BILLS ON TIME TO AVOID LATE FEES | $576 | $0 | Implemented |
MZ0199 # 02 Y:2015 | 02 | 2015 | CONDENSE OPERATION INTO ONE BUILDING | $19,376 | $2,500 | Not Implemented |
MZ0199 # 01 Y:2015 | 01 | 2015 | CONDENSE OPERATION INTO ONE BUILDING | $14,201 | $28,800 | Not Implemented |
IP0053 # 03 Y:2015 | 03 | 2015 | APPLY FOR INVESTMENT INCENTIVES | $38,029 | $5,000 | Implemented |
IP0052 # 08 Y:2015 | 08 | 2015 | APPLY FOR INVESTMENT INCENTIVES | $12,926 | $10,000 | Implemented |
IP0049 # 08 Y:2015 | 08 | 2015 | APPLY FOR INVESTMENT INCENTIVES | $7,789 | $10,000 | Not Implemented |
IP0049 # 01 Y:2015 | 01 | 2015 | PAY BILLS ON TIME TO AVOID LATE FEES | $4,118 | $0 | Implemented |
OR0662 # 01 Y:2015 | 01 | 2015 | REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | $41,305 | $102,204 | Not Implemented |
BS0066 # 06 Y:2015 | 06 | 2015 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $13,061 | $19,065 | Not Implemented |
OR0662 # 02 Y:2015 | 02 | 2015 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $15,820 | $2,500 | Not Implemented |
MZ0198 # 04 Y:2015 | 04 | 2015 | CONDENSE OPERATION INTO ONE BUILDING | $17,298 | $1,040 | Implemented |
MZ0190 # 02 Y:2015 | 02 | 2015 | CONDENSE OPERATION INTO ONE BUILDING | $12,608 | $0 | Not Implemented |
MZ0190 # 03 Y:2015 | 03 | 2015 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $20,868 | $40,000 | Not Implemented |
SU0396 # 01 Y:2015 | 01 | 2015 | PAY BILLS ON TIME TO AVOID LATE FEES | $813 | $0 | Implemented |
IP0048 # 07 Y:2015 | 07 | 2015 | APPLY FOR INVESTMENT INCENTIVES | $8,854 | $4,500 | Not Implemented |
IP0048 # 08 Y:2015 | 08 | 2015 | APPLY FOR INVESTMENT INCENTIVES | $15,491 | $9,000 | Not Implemented |
IP0047 # 06 Y:2015 | 06 | 2015 | APPLY FOR INVESTMENT INCENTIVES | $10,288 | $5,000 | Implemented |
IP0047 # 05 Y:2015 | 05 | 2015 | APPLY FOR INVESTMENT INCENTIVES | $30,801 | $10,000 | Implemented |
OR0658 # 01 Y:2015 | 01 | 2015 | MODIFY CURRENT INCENTIVE PROGRAM | $22,712 | $60,000 | Not Implemented |
SU0392 # 01 Y:2015 | 01 | 2015 | PAY BILLS ON TIME TO AVOID LATE FEES | $4,042 | $0 | Implemented |
OR0656 # 01 Y:2015 | 01 | 2015 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $2,308,919 | $1,300,000 | Implemented |
OR0655 # 06 Y:2015 | 06 | 2015 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $180,695 | $251,760 | Not Implemented |
OR0654 # 03 Y:2015 | 03 | 2015 | MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS | $115,650 | $50,000 | Implemented |