IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

47

matching recommendations
Reset
ARC 4. DIRECT PRODUCTIVITY ENHANCEMENTS
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AM0696 # 02 Y:2015 02 2015 MODIFY WORKLOAD $8,280 $0 Not Implemented
SU0401 # 01 Y:2015 01 2015 PAY BILLS ON TIME TO AVOID LATE FEES $2,820 $0 Implemented
IP0054 # 02 Y:2015 02 2015 PAY BILLS ON TIME TO AVOID LATE FEES $576 $0 Implemented
MZ0199 # 02 Y:2015 02 2015 CONDENSE OPERATION INTO ONE BUILDING $19,376 $2,500 Not Implemented
MZ0199 # 01 Y:2015 01 2015 CONDENSE OPERATION INTO ONE BUILDING $14,201 $28,800 Not Implemented
IP0053 # 03 Y:2015 03 2015 APPLY FOR INVESTMENT INCENTIVES $38,029 $5,000 Implemented
IP0052 # 08 Y:2015 08 2015 APPLY FOR INVESTMENT INCENTIVES $12,926 $10,000 Implemented
IP0049 # 08 Y:2015 08 2015 APPLY FOR INVESTMENT INCENTIVES $7,789 $10,000 Not Implemented
IP0049 # 01 Y:2015 01 2015 PAY BILLS ON TIME TO AVOID LATE FEES $4,118 $0 Implemented
OR0662 # 01 Y:2015 01 2015 REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL $41,305 $102,204 Not Implemented
BS0066 # 06 Y:2015 06 2015 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST $13,061 $19,065 Not Implemented
OR0662 # 02 Y:2015 02 2015 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $15,820 $2,500 Not Implemented
MZ0198 # 04 Y:2015 04 2015 CONDENSE OPERATION INTO ONE BUILDING $17,298 $1,040 Implemented
MZ0190 # 02 Y:2015 02 2015 CONDENSE OPERATION INTO ONE BUILDING $12,608 $0 Not Implemented
MZ0190 # 03 Y:2015 03 2015 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS $20,868 $40,000 Not Implemented
SU0396 # 01 Y:2015 01 2015 PAY BILLS ON TIME TO AVOID LATE FEES $813 $0 Implemented
IP0048 # 07 Y:2015 07 2015 APPLY FOR INVESTMENT INCENTIVES $8,854 $4,500 Not Implemented
IP0048 # 08 Y:2015 08 2015 APPLY FOR INVESTMENT INCENTIVES $15,491 $9,000 Not Implemented
IP0047 # 06 Y:2015 06 2015 APPLY FOR INVESTMENT INCENTIVES $10,288 $5,000 Implemented
IP0047 # 05 Y:2015 05 2015 APPLY FOR INVESTMENT INCENTIVES $30,801 $10,000 Implemented
OR0658 # 01 Y:2015 01 2015 MODIFY CURRENT INCENTIVE PROGRAM $22,712 $60,000 Not Implemented
SU0392 # 01 Y:2015 01 2015 PAY BILLS ON TIME TO AVOID LATE FEES $4,042 $0 Implemented
OR0656 # 01 Y:2015 01 2015 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $2,308,919 $1,300,000 Implemented
OR0655 # 06 Y:2015 06 2015 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $180,695 $251,760 Not Implemented
OR0654 # 03 Y:2015 03 2015 MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS $115,650 $50,000 Implemented