IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

96

matching recommendations
Reset
ARC 2.12 BOILERS
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
DL0010 # 04 Y:2007 04 2007 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,529 $450 Implemented
DL0010 # 02 Y:2007 02 2007 INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) $9,440 $2,500 Not Implemented
BD0338 # 06 Y:2007 06 2007 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES $369,530 $30,001 Not Implemented
BD0338 # 07 Y:2007 07 2007 REPLACE BOILER $36,792 $110,001 Implemented
MI0158 # 10 Y:2007 10 2007 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $3,886 $2,000 Implemented
DL0009 # 03 Y:2007 03 2007 INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) $11,200 $60,000 Not Implemented
IA0416 # 05 Y:2007 05 2007 DIRECT WARMEST AIR TO COMBUSTION INTAKE $1,251 $1,500 Not Implemented
BD0334 # 02 Y:2007 02 2007 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES $210,390 $615,001 Not Implemented
UM0333 # 01 Y:2007 01 2007 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $19,901 $2,000 Implemented
UM0332 # 02 Y:2007 02 2007 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $56,464 $1,000 Implemented
GT0844 # 04 Y:2007 04 2007 REDUCE EXCESSIVE BOILER BLOWDOWN $44,955 $10,000 Not Implemented
GT0844 # 01 Y:2007 01 2007 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $19,992 $28,800 Not Implemented
GT0844 # 03 Y:2007 03 2007 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $71,952 $14,867 Not Implemented
IA0415 # 05 Y:2007 05 2007 DIRECT WARMEST AIR TO COMBUSTION INTAKE $4,262 $1,500 Implemented
UD0768 # 05 Y:2007 05 2007 REPLACE BOILER $5,791 $40,000 Not Implemented
UD0768 # 09 Y:2007 09 2007 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $860 $0 Implemented
CO0608 # 04 Y:2007 04 2007 REPLACE BOILER $23,660 $20,000 Implemented
DL0008 # 02 Y:2007 02 2007 REPLACE BOILER $33,159 $102,000 Not Implemented
DL0008 # 06 Y:2007 06 2007 REPLACE BOILER $12,509 $27,400 Not Implemented
NC0370 # 03 Y:2007 03 2007 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $48,420 $25,000 Not Implemented
IC0132 # 07 Y:2007 07 2007 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $396 $0 Implemented
LE0263 # 05 Y:2007 05 2007 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $25,485 $20,000 Not Implemented
NC0369 # 05 Y:2007 05 2007 KEEP BOILER TUBES CLEAN $2,955 $1,000 Implemented
LL0284 # 04 Y:2007 04 2007 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $16,900 $1,500 Not Implemented
DL0007 # 07 Y:2007 07 2007 REPLACE BOILER $1,325 $10,425 Implemented