Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
50
matching recommendationsARC | 4. | DIRECT PRODUCTIVITY ENHANCEMENTS |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LS2009 # 07 Y:2020 | 07 | 2020 | INSTALL AUTOMATIC PACKING EQUIPMENT | $57,969 | $120,000 | Implemented |
UF0560 # 08 Y:2020 | 08 | 2020 | MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS | $9,639 | $725 | Implemented |
UF0560 # 07 Y:2020 | 07 | 2020 | LEVEL THREE - INSTALL OR MODIFY CONTROL SYSTEM WITH COMMUNICATION AND NONLOCAL EXTERNAL INFORMATION (I.E. WEATHER FORECA | $134,615 | $11,004 | Not Implemented |
UF0559 # 08 Y:2020 | 08 | 2020 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $5,262 | $7,180 | Implemented |
UF0558 # 03 Y:2020 | 03 | 2020 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $42,983 | $7,127 | Implemented |
CL2015 # 01 Y:2020 | 01 | 2020 | MODIFY STARTUP/SHUTDOWN TIMES | $7,855 | $550 | Not Implemented |
IP0142 # 01 Y:2020 | 01 | 2020 | PAY BILLS ON TIME TO AVOID LATE FEES | $580 | $0 | Not Implemented |
UF0555 # 05 Y:2020 | 05 | 2020 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $340,000 | $5,859 | Implemented |
UD1025 # 10 Y:2020 | 10 | 2020 | INSTALL EQUIPMENT TO MOVE PRODUCT | $454,408 | $375,000 | Not Implemented |
UA0234 # 01 Y:2020 | 01 | 2020 | MODIFY STARTUP/SHUTDOWN TIMES | $17,505 | $0 | Implemented |
IP0141 # 03 Y:2020 | 03 | 2020 | APPLY FOR INVESTMENT INCENTIVES | $15,156 | $10,000 | Implemented |
IP0141 # 04 Y:2020 | 04 | 2020 | APPLY FOR INVESTMENT INCENTIVES | $2,218 | $2,000 | Implemented |
MZ0296 # 06 Y:2020 | 06 | 2020 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $100,865 | $197,145 | Not Implemented |
MZ0296 # 07 Y:2020 | 07 | 2020 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $57,876 | $199,418 | Not Implemented |
NC0652 # 06 Y:2020 | 06 | 2020 | CONDENSE OPERATION INTO ONE BUILDING | $6,086 | $4,800 | Not Implemented |
CL2011 # 04 Y:2020 | 04 | 2020 | MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS | $7,830 | $4,500 | Implemented |
CL2010 # 04 Y:2020 | 04 | 2020 | MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS | $14,466 | $4,500 | Implemented |
UF0554 # 04 Y:2020 | 04 | 2020 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $9,363 | $0 | Implemented |
UF0554 # 05 Y:2020 | 05 | 2020 | INSTALL SENSORS TO DETECT DEFECTS | $3,851 | $15,420 | Implemented |
UF0553 # 05 Y:2020 | 05 | 2020 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $2,236 | $0 | Implemented |
UF0553 # 01 Y:2020 | 01 | 2020 | AUTOMATE FINISHING PROCESS | $20,196 | $46,226 | Not Implemented |
UF0553 # 04 Y:2020 | 04 | 2020 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $395,494 | $1,875,550 | Not Implemented |
UF0552 # 06 Y:2020 | 06 | 2020 | INSTALL AN UNINTERUPTABLE POWER SUPPLY | $45,577 | $65,793 | Implemented |
UF0552 # 01 Y:2020 | 01 | 2020 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $23,402 | $0 | Implemented |
IP0140 # 01 Y:2020 | 01 | 2020 | PAY BILLS ON TIME TO AVOID LATE FEES | $266 | $0 | Not Implemented |