IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

47

matching recommendations
Reset
ARC 4 DIRECT PRODUCTIVITY ENHANCEMENTS
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CL1909 # 04 Y:2019 04 2019 PAY BILLS ON TIME TO AVOID LATE FEES $2,971 $0 Implemented
UA0211 # 09 Y:2019 09 2019 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $2,027,932 $1,000,000 Not Implemented
AM0783 # 01 Y:2019 01 2019 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $53,720 $50,000 Implemented
TT0223 # 07 Y:2019 07 2019 APPLY FOR INVESTMENT INCENTIVES $4,144 $40 Not Implemented
AS0472 # 04 Y:2019 04 2019 USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES $4,878 $6,000 Not Implemented
CL1908 # 06 Y:2019 06 2019 APPLY FOR INVESTMENT INCENTIVES $397 $0 Not Implemented
MZ0272 # 07 Y:2019 07 2019 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST $31,952 $68,000 Not Implemented
CL1907 # 01 Y:2019 01 2019 PAY BILLS ON TIME TO AVOID LATE FEES $4,250 $4,250 Implemented
UF0527 # 07 Y:2019 07 2019 INSTALL AN UNINTERUPTABLE POWER SUPPLY $24,935 $1,665 Implemented
OK1007 # 05 Y:2019 05 2019 INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM $96,866 $35,244 Not Implemented
GT0922 # 05 Y:2019 05 2019 PAY BILLS ON TIME TO AVOID LATE FEES $281 $1,190 Implemented
UF0525 # 08 Y:2019 08 2019 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $35,380 $15,216 Not Implemented
UF0525 # 09 Y:2019 09 2019 REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL $34,636 $10,000 Not Implemented
UU0145 # 01 Y:2019 01 2019 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $377,567 $872,000 Not Implemented
TT0219 # 09 Y:2019 09 2019 APPLY FOR INVESTMENT INCENTIVES $1,440 $0 Implemented
OK1000 # 01 Y:2019 01 2019 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST $2,438 $8,400 Not Implemented
OR0716 # 01 Y:2019 01 2019 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST $170,737 $8,015 Not Implemented
MI0346 # 03 Y:2019 03 2019 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS $10,140 $8,840 Not Implemented
AS0465 # 03 Y:2019 03 2019 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $41,936 $1,100 Not Implemented
SU0475 # 01 Y:2019 01 2019 PAY BILLS ON TIME TO AVOID LATE FEES $388 $0 Implemented
UA0205 # 04 Y:2019 04 2019 MODIFY STARTUP/SHUTDOWN TIMES $280 $0 Implemented
LS1901 # 05 Y:2019 05 2019 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $45,500 $27,000 Not Implemented