IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

6,717

matching recommendations
Reset
ARC 4. DIRECT PRODUCTIVITY ENHANCEMENTS
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WV0213 # 09 Y:2001 09 2001 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $20,000 $7,000 Not Implemented
WV0213 # 10 Y:2001 10 2001 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $20,000 $12,000 Not Implemented
LM0007 # 07 Y:2001 07 2001 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS $29,913 $29,612 Implemented
LM0006 # 06 Y:2001 06 2001 MODIFY STARTUP/SHUTDOWN TIMES $11,340 $1,000 Not Implemented
AS0297 # 06 Y:2001 06 2001 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY $5,712 $5,916 Not Implemented
UF0241 # 07 Y:2000 07 2000 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY $12,880 $9,000 Implemented
UF0242 # 08 Y:2000 08 2000 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY $12,880 $9,000 Implemented
OR0390 # 01 Y:2001 01 2001 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST $79,800 $30,700 Implemented
UF0241 # 03 Y:2000 03 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $122,360 $141,700 Not Implemented
UF0241 # 06 Y:2000 06 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $1,741,926 $6,200,000 Not Implemented
UF0242 # 03 Y:2000 03 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $122,360 $141,700 Not Implemented
UF0242 # 07 Y:2000 07 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $1,741,926 $6,200,000 Not Implemented
OR0389 # 01 Y:2001 01 2001 MODIFY CURRENT INCENTIVE PROGRAM $289,800 $26,680 Implemented
IC0006 # 06 Y:2001 06 2001 ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL $300,000 $8,500 Not Implemented
AM0399 # 01 Y:2001 01 2001 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST $183,100 $150,000 Not Implemented
AM0399 # 02 Y:2001 02 2001 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST $107,750 $120,000 Not Implemented
IC0006 # 07 Y:2001 07 2001 MODIFY WORKLOAD $65,000 $5,500 Implemented
IC0006 # 08 Y:2001 08 2001 INSTALL AUTOMATIC PACKING EQUIPMENT $21,000 $53,000 Not Implemented
LM0005 # 05 Y:2001 05 2001 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY $168,480 $45,830 Not Implemented
LM0005 # 06 Y:2001 06 2001 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS $6,000 $5,000 Not Implemented
LM0005 # 04 Y:2001 04 2001 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $3,600 $0 Not Implemented
UF0273 # 02 Y:2001 02 2001 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $916 $525 Implemented
UF0273 # 10 Y:2001 10 2001 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $59,693 $4,000 Implemented
UF0274 # 13 Y:2001 13 2001 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $108,000 $900,000 Implemented
SD0278 # 08 Y:2001 08 2001 AUTOMATE FINISHING PROCESS $100,600 $120,000 Not Implemented