IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

6,860

matching recommendations
Reset
ARC 2.3 Electrical Power
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0469 # 08 Y:2004 08 2004 OPTIMIZE PLANT POWER FACTOR $4,610 $14,750 Not Implemented
SU0197 # 09 Y:2004 09 2004 OPTIMIZE PLANT POWER FACTOR $2,001 $6,941 Implemented
WI0477 # 01 Y:2004 01 2004 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $10,743 $0 Not Implemented
NC0296 # 02 Y:2004 02 2004 USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS $22,518 $10,000 Not Implemented
OR0465 # 05 Y:2004 05 2004 OPTIMIZE PLANT POWER FACTOR $35,600 $55,000 Implemented
LE0198 # 02 Y:2004 02 2004 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,500 $2,500 Implemented
UD0704 # 02 Y:2004 02 2004 OPTIMIZE PLANT POWER FACTOR $3,335 $6,000 Not Implemented
MS0259 # 05 Y:2004 05 2004 HEAT WATER DURING OFF-PEAK PERIODS AND STORE FOR LATER USE $6,267 $18,138 Not Implemented
MA0560 # 03 Y:2004 03 2004 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $5,875 $1,200 Implemented
OK0693 # 03 Y:2004 03 2004 OPTIMIZE PLANT POWER FACTOR $7,010 $10,720 n/a
CO0549 # 01 Y:2004 01 2004 USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR $29,210 $116,000 Not Implemented
WV0302 # 02 Y:2004 02 2004 USE DEMAND CONTROLLER OR LOAD SHEDDER $3,141 $0 Implemented
LE0196 # 08 Y:2004 08 2004 OPTIMIZE PLANT POWER FACTOR $7,875 $11,050 Not Implemented
LE0196 # 03 Y:2004 03 2004 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $19,639 $5,000 Implemented
WV0292 # 03 Y:2004 03 2004 OPTIMIZE PLANT POWER FACTOR $19,410 $20,490 Not Implemented
SU0194 # 07 Y:2004 07 2004 DE-ENERGIZE EXCESS TRANSFORMER CAPACITY $1,122 $2,975 Not Implemented
IC0085 # 02 Y:2004 02 2004 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,699 $0 Implemented
UU0066 # 05 Y:2004 05 2004 OPTIMIZE PLANT POWER FACTOR $81 $270 Not Implemented
IC0087 # 05 Y:2004 05 2004 USE STEAM PRESSURE REDUCTION TO GENERATE POWER $53,985 $1,560 Not Implemented
LE0194 # 05 Y:2004 05 2004 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $4,360 $2,500 Not Implemented
TA0079 # 07 Y:2004 07 2004 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $280 $0 Implemented
UU0065 # 02 Y:2004 02 2004 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $6,450 $0 Implemented
UU0065 # 01 Y:2004 01 2004 OPTIMIZE PLANT POWER FACTOR $4,060 $5,520 Not Implemented
LE0195 # 01 Y:2004 01 2004 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT $575,674 $984,000 Not Implemented
LL0199 # 04 Y:2004 04 2004 OPTIMIZE PLANT POWER FACTOR $4,382 $24,514 Not Implemented