Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
6,706
matching recommendationsARC | 4. | DIRECT PRODUCTIVITY ENHANCEMENTS |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AR0118 # 12 Y:1997 | 12 | 1997 | REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | $100,000 | $240,000 | Not Implemented |
BD0088 # 09 Y:1997 | 09 | 1997 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $4,211 | $0 | Not Implemented |
HO0159 # 06 Y:1997 | 06 | 1997 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $1,920 | $500 | Not Implemented |
NV0081 # 07 Y:1997 | 07 | 1997 | REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | $1,164 | $2,120 | Implemented |
NV0081 # 08 Y:1997 | 08 | 1997 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $30,328 | $155,000 | Not Implemented |
NV0081 # 09 Y:1997 | 09 | 1997 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $60,656 | $12,000 | Implemented |
NV0081 # 10 Y:1997 | 10 | 1997 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $15,164 | $20,000 | Not Implemented |
NV0081 # 12 Y:1997 | 12 | 1997 | USE ONLY AMOUNT OF PACKAGING MATERIAL NECESSARY | $2,040 | $0 | Not Implemented |
SD0177 # 12 Y:1997 | 12 | 1997 | INSTALL SYSTEM TO COLLECT SCRAP | $69,638 | $20,000 | Implemented |
SF0118 # 11 Y:1997 | 11 | 1997 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $46,724 | $32,060 | Implemented |
WV0121 # 08 Y:1997 | 08 | 1997 | CLEAR AND RENT EXISTING SPACE | $4,000 | $1,600 | Implemented |
WV0122 # 07 Y:1997 | 07 | 1997 | INSTALL AUTOMATIC PACKING EQUIPMENT | $20,000 | $90,000 | Not Implemented |
WV0122 # 08 Y:1997 | 08 | 1997 | MOVE PRODUCT USING MECHANICAL MEANS | $104,000 | $3,000 | Not Implemented |
KG0095 # 09 Y:1997 | 09 | 1997 | MOVE PRODUCT USING MECHANICAL MEANS | $22,327 | $11,750 | n/a |
KG0095 # 10 Y:1997 | 10 | 1997 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $39,600 | $6,000 | n/a |
NV0080 # 06 Y:1997 | 06 | 1997 | ELIMINATE/REDUCE REDUNDANT INSPECTIONS | $14,966 | $7,500 | Implemented |
GT0617 # 05 Y:1997 | 05 | 1997 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $139,500 | $155,000 | Not Implemented |
GT0617 # 07 Y:1997 | 07 | 1997 | INSTALL AUTOMATIC PACKING EQUIPMENT | $125,400 | $150,000 | Not Implemented |
HO0158 # 05 Y:1997 | 05 | 1997 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $2,500 | $1,000 | Implemented |
SD0176 # 07 Y:1997 | 07 | 1997 | INSTALL AUTOMATIC PACKING EQUIPMENT | $133,998 | $30,000 | Implemented |
SD0176 # 08 Y:1997 | 08 | 1997 | INSTALL SYSTEM TO COLLECT SCRAP | $618,145 | $200,000 | Not Implemented |
MS0087 # 08 Y:1997 | 08 | 1997 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $46,844 | $20,800 | Not Implemented |
MO0202 # 01 Y:1997 | 01 | 1997 | INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM | $34,950 | $25,000 | Implemented |
MO0202 # 02 Y:1997 | 02 | 1997 | CROSS-TRAIN PERSONNEL TO AVOID LOST TIME | $14,720 | $20,000 | Implemented |
MO0202 # 03 Y:1997 | 03 | 1997 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $11,610 | $3,500 | Implemented |