IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

126

matching recommendations
Reset
ARC 2.3 Electrical Power
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UU0136 # 03 Y:2018 03 2018 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $14,124 $0 Not Implemented
MA0790 # 01 Y:2018 01 2018 USE DEMAND CONTROLLER OR LOAD SHEDDER $207,219 $1,000,000 Not Implemented
UU0136 # 01 Y:2018 01 2018 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT $159,197 $1,737,000 Not Implemented
OK0988 # 01 Y:2018 01 2018 OPTIMIZE PLANT POWER FACTOR $7,394 $12,000 Not Implemented
MZ0256 # 07 Y:2018 07 2018 OPTIMIZE PLANT POWER FACTOR $4,834 $26,380 Not Implemented
SU0461 # 02 Y:2018 02 2018 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $3,138 $700 Implemented
MI0336 # 01 Y:2018 01 2018 USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS $21,620 $80 Implemented
WM0123 # 12 Y:2018 12 2018 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $207 $0 Implemented
WV0561 # 05 Y:2018 05 2018 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,253 $6,000 Not Implemented
SU0460 # 08 Y:2018 08 2018 OPTIMIZE PLANT POWER FACTOR $5,002 $8,529 Not Implemented
SD0566 # 01 Y:2018 01 2018 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $100,744 $336,960 Implemented
MI0333 # 06 Y:2018 06 2018 USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS $4,911 $80 Implemented
SD0565 # 02 Y:2018 02 2018 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $14,497 $72,900 Not Implemented
NC0611 # 06 Y:2018 06 2018 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,662 $200 Implemented
AM0756 # 01 Y:2018 01 2018 OPTIMIZE PLANT POWER FACTOR $7,920 $17,500 Not Implemented
TR0009 # 01 Y:2018 01 2018 OPTIMIZE PLANT POWER FACTOR $3,043 $12,500 Not Implemented
SF0520 # 09 Y:2018 09 2018 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $2,289 $953 Implemented
SD0564 # 01 Y:2018 01 2018 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $17,517 $86,400 Implemented
AS0454 # 05 Y:2018 05 2018 MAKE ICE DURING OFF PEAK HOURS FOR COOLING $11,530 $150 Not Implemented
TT0209 # 04 Y:2018 04 2018 OPTIMIZE PLANT POWER FACTOR $6,114 $5,200 Not Implemented
SD0563 # 01 Y:2018 01 2018 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $22,261 $80,415 Not Implemented
AM0754 # 02 Y:2018 02 2018 OPTIMIZE PLANT POWER FACTOR $7,740 $11,520 Implemented
MZ0255 # 05 Y:2018 05 2018 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $6,457 $3,200 Not Implemented
MZ0255 # 01 Y:2018 01 2018 OPTIMIZE PLANT POWER FACTOR $47,570 $16,500 Implemented
UF0516 # 01 Y:2018 01 2018 USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST $120,914 $400,000 Not Implemented