Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,654
matching recommendationsARC | 4 | DIRECT PRODUCTIVITY ENHANCEMENTS |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0313 # 09 Y:2003 | 09 | 2003 | INSTALL SYSTEM TO COLLECT SCRAP | $1,808 | $700 | Implemented |
AM0427 # 01 Y:2003 | 01 | 2003 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $11,250 | $500 | Implemented |
LM0047 # 10 Y:2003 | 10 | 2003 | SCHEDULE DELIVERIES ACCORDING TO DEMAND | $63,000 | $5,000 | Implemented |
LM0047 # 08 Y:2003 | 08 | 2003 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $138,235 | $2,000 | Implemented |
LM0047 # 07 Y:2003 | 07 | 2003 | DEVELOP STANDARD OPERATING PROCEDURES | $250,000 | $26,500 | Implemented |
LM0047 # 09 Y:2003 | 09 | 2003 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $31,500 | $2,000 | Implemented |
BD0222 # 14 Y:2002 | 14 | 2002 | AUTOMATE PAYROLL SYSTEM | $24,960 | $17,300 | Implemented |
BD0222 # 13 Y:2002 | 13 | 2002 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $70,000 | $40,000 | Implemented |
SD0309 # 10 Y:2003 | 10 | 2003 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $11,200 | $2,500 | Implemented |
AM0425 # 08 Y:2003 | 08 | 2003 | PAY BILLS ON TIME TO AVOID LATE FEES | $2,006 | $0 | Implemented |
AM0425 # 02 Y:2003 | 02 | 2003 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $243,880 | $16,000 | Implemented |
AM0425 # 03 Y:2003 | 03 | 2003 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $154,000 | $2,000 | Implemented |
LL0152 # 06 Y:2003 | 06 | 2003 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $8,995 | $12,400 | Implemented |
LL0151 # 08 Y:2003 | 08 | 2003 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $9,556 | $12,425 | Implemented |
AM0423 # 09 Y:2002 | 09 | 2002 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $27,800 | $18,880 | Implemented |
AM0423 # 10 Y:2002 | 10 | 2002 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $18,500 | $15,780 | Implemented |
AS0340 # 13 Y:2002 | 13 | 2002 | CLEAR AND RENT EXISTING SPACE | $60,660 | $8,804 | Implemented |
AS0340 # 11 Y:2002 | 11 | 2002 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $25,624 | $4,800 | Implemented |
OR0424 # 05 Y:2002 | 05 | 2002 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $69,350 | $46,000 | Implemented |
AS0339 # 04 Y:2002 | 04 | 2002 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $113,273 | $9,000 | Implemented |
TA0044 # 01 Y:2002 | 01 | 2002 | HIRE ADDITIONAL PERSONNEL TO REDUCE CHANGEOUT TIME | $114,400 | $0 | Implemented |
AS0336 # 09 Y:2002 | 09 | 2002 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $3,820 | $2,080 | Implemented |
AS0336 # 08 Y:2002 | 08 | 2002 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $72,604 | $3,840 | Implemented |
OK0647 # 07 Y:2002 | 07 | 2002 | INSTALL EQUIPMENT TO MOVE PRODUCT | $166,400 | $208,754 | Implemented |
SU0148 # 03 Y:2002 | 03 | 2002 | MODIFY WORKLOAD | $14,400 | $20,000 | Implemented |