IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

6,754

matching recommendations
Reset
ARC 4 DIRECT PRODUCTIVITY ENHANCEMENTS
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
HO0232 # 14 Y:2000 14 2000 CLEAR AND RENT EXISTING SPACE $341,986 $1,000 Not Implemented
TN0691 # 01 Y:2000 01 2000 INITIATE A PROGRAM TO ACQUIRE ISO CERTIFICATION $144,950 $100,000 Not Implemented
HO0232 # 12 Y:2000 12 2000 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $2,400 $1,035 Not Implemented
HO0232 # 13 Y:2000 13 2000 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $840 $25 Not Implemented
HO0232 # 18 Y:2000 18 2000 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $1,500 $368 Not Implemented
HO0232 # 19 Y:2000 19 2000 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $5,360 $6,240 Not Implemented
DS0169 # 09 Y:2000 09 2000 INSTALL SHELVES / RACKS TO UTILIZE UNUSED SPACE $600 $1,288 Implemented
MO0281 # 07 Y:2000 07 2000 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $18,160 $3,700 Not Implemented
CO0468 # 10 Y:2000 10 2000 MODIFY STARTUP/SHUTDOWN TIMES $3,310 $1,770 Implemented
WV0199 # 12 Y:2000 12 2000 INSTALL AUTOMATIC PACKING EQUIPMENT $124,800 $360,000 Not Implemented
CO0468 # 09 Y:2000 09 2000 INSTALL EQUIPMENT TO MOVE PRODUCT $5,620 $100 Implemented
MO0281 # 08 Y:2000 08 2000 INSTALL EQUIPMENT TO MOVE PRODUCT $14,183 $2,580 Not Implemented
CO0468 # 08 Y:2000 08 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $58,970 $60,000 Implemented
DS0169 # 08 Y:2000 08 2000 CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE $5,929 $12,962 Implemented
OD0165 # 05 Y:2000 05 2000 CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE $31,722 $0 Implemented
OK0599 # 07 Y:2000 07 2000 PURCHASE APPROPRIATELY SIZED MATERIAL $224,052 $150 Not Implemented
OK0599 # 06 Y:2000 06 2000 REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL $200,000 $300,000 Not Implemented
SF0195 # 08 Y:2000 08 2000 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $27,873 $2,000 Not Implemented
SD0255 # 09 Y:2000 09 2000 INSTALL EQUIPMENT TO MOVE PRODUCT $25,800 $23,000 Not Implemented
NC0191 # 08 Y:2000 08 2000 RESCHEDULE BREAKS TO ALLOW FOR CONTINUOUS PRODUCTION $6,729 $288 Not Implemented
AS0281 # 08 Y:2000 08 2000 MODIFY STARTUP/SHUTDOWN TIMES $8,782 $9,600 Not Implemented
TN0690 # 02 Y:2000 02 2000 INSTALL EQUIPMENT TO MOVE PRODUCT $164,990 $183,505 Implemented
OD0164 # 01 Y:2000 01 2000 CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE $4,040 $0 Not Implemented
AS0281 # 09 Y:2000 09 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $31,250 $15,000 Not Implemented
WV0198 # 11 Y:2000 11 2000 INSTALL SENSORS TO DETECT DEFECTS $8,580 $125 Implemented