Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
6,709
matching recommendationsARC | 4. | DIRECT PRODUCTIVITY ENHANCEMENTS |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0358 # 08 Y:2007 | 08 | 2007 | MAINTAIN CLEAN CONDITIONS BEFORE PAINTING | $805,000 | $56,000 | Not Implemented |
OK0744 # 05 Y:2007 | 05 | 2007 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $800 | $0 | Not Implemented |
LM0124 # 01 Y:2007 | 01 | 2007 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $7,858 | $2,500 | Implemented |
LM0124 # 03 Y:2007 | 03 | 2007 | SCHEDULE DELIVERIES ACCORDING TO DEMAND | $151,200 | $2,000 | Implemented |
LM0124 # 04 Y:2007 | 04 | 2007 | INSTALL SENSORS TO DETECT AND AVOID JAMS | $15,120 | $1,400 | Not Implemented |
LM0124 # 05 Y:2007 | 05 | 2007 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $44,787 | $1,000 | Implemented |
LM0124 # 06 Y:2007 | 06 | 2007 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $34,678 | $2,000 | Implemented |
MS0314 # 02 Y:2007 | 02 | 2007 | PURCHASE EQUIPMENT INSTEAD OF LEASING | $3,612 | $10,968 | Not Implemented |
UA0001 # 05 Y:2007 | 05 | 2007 | UTILIZE JOB COSTING SOFTWARE | $31,200 | $8,489 | Not Implemented |
LL0269 # 06 Y:2007 | 06 | 2007 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $6,878 | $164 | Implemented |
LL0269 # 12 Y:2007 | 12 | 2007 | PAY BILLS ON TIME TO AVOID LATE FEES | $118 | $0 | Not Implemented |
UF0396 # 12 Y:2007 | 12 | 2007 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $7,488 | $970 | Not Implemented |
OR0514 # 05 Y:2007 | 05 | 2007 | DEVELOP STANDARD OPERATING PROCEDURES | $204,000 | $18,800 | Not Implemented |
LL0267 # 09 Y:2007 | 09 | 2007 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $3,060 | $2,034 | Not Implemented |
LL0266 # 09 Y:2007 | 09 | 2007 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $1,920 | $1,325 | Not Implemented |
MA0610 # 02 Y:2007 | 02 | 2007 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $5,760 | $7,600 | Implemented |
SU0248 # 03 Y:2007 | 03 | 2007 | PAY BILLS ON TIME TO AVOID LATE FEES | $546 | $0 | Implemented |
UD0753 # 01 Y:2007 | 01 | 2007 | DEVELOP STANDARD OPERATING PROCEDURES | $98,450 | $3,040 | Implemented |
LL0268 # 10 Y:2007 | 10 | 2007 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $6,201 | $382 | Not Implemented |
LM0123 # 04 Y:2007 | 04 | 2007 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $37,630 | $1,000 | Not Implemented |
BD0318 # 01 Y:2007 | 01 | 2007 | AUTOMATE PAYROLL SYSTEM | $15,000 | $10,500 | Not Implemented |
LM0122 # 04 Y:2007 | 04 | 2007 | ELIMINATE/REDUCE REDUNDANT INSPECTIONS | $19,128 | $5,500 | Implemented |
LM0122 # 05 Y:2007 | 05 | 2007 | MODIFY WORKLOAD | $9,311 | $4,850 | Implemented |
AM0520 # 03 Y:2007 | 03 | 2007 | MOVE PRODUCT USING MECHANICAL MEANS | $57,600 | $4,500 | Not Implemented |
AM0520 # 11 Y:2007 | 11 | 2007 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $9,140 | $35,000 | Implemented |