IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

6,846

matching recommendations
Reset
ARC 2.3 Electrical Power
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
TT0199 # 03 Y:2017 03 2017 OPTIMIZE PLANT POWER FACTOR $5,729 $8,000 Not Implemented
UD0977 # 07 Y:2017 07 2017 OPTIMIZE PLANT POWER FACTOR $3,320 $6,000 Not Implemented
UF0512 # 03 Y:2017 03 2017 OPTIMIZE PLANT POWER FACTOR $38,189 $13,000 Implemented
UF0512 # 01 Y:2017 01 2017 USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST $401,159 $2,500,000 Not Implemented
UF0512 # 04 Y:2017 04 2017 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $23,030 $40,000 Not Implemented
TR0006 # 08 Y:2017 08 2017 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $23,655 $0 n/a
AM0739 # 02 Y:2017 02 2017 OPTIMIZE PLANT POWER FACTOR $17,900 $28,900 Not Implemented
UK1710 # 06 Y:2017 06 2017 OPTIMIZE PLANT POWER FACTOR $8,180 $18,216 Not Implemented
SD0556 # 01 Y:2017 01 2017 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $57,756 $205,000 Implemented
MZ0240 # 07 Y:2017 07 2017 USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS $119,328 $208,000 Implemented
UD0976 # 01 Y:2017 01 2017 OPTIMIZE PLANT POWER FACTOR $2,704 $1,000 Not Implemented
UK1708 # 09 Y:2017 09 2017 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT $22,096 $78,750 Not Implemented
LE0444 # 11 Y:2017 11 2017 CONSIDER POWER LOSS AS WELL AS INITIAL LOADS AND LOAD GROWTH IN DOWN-SIZING TRANSFORMERS $233,480 $1,905,000 Implemented
SD0555 # 01 Y:2017 01 2017 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $18,916 $65,600 Not Implemented
AM0738 # 01 Y:2017 01 2017 OPTIMIZE PLANT POWER FACTOR $23,860 $39,900 Implemented
UK1707 # 16 Y:2017 16 2017 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $10,352 $0 Not Implemented
UK1707 # 10 Y:2017 10 2017 OPTIMIZE PLANT POWER FACTOR $81,973 $62,685 Implemented
OK0977 # 06 Y:2017 06 2017 OPTIMIZE PLANT POWER FACTOR $16,088 $1,209 Not Implemented
OK0975 # 01 Y:2017 01 2017 OPTIMIZE PLANT POWER FACTOR $25,427 $24,531 Not Implemented
OK0973 # 12 Y:2017 12 2017 OPTIMIZE PLANT POWER FACTOR $17,217 $17,024 Not Implemented
IP0090 # 07 Y:2017 07 2017 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT $3,206,016 $2,150,000 Not Implemented
OK0978 # 01 Y:2017 01 2017 OPTIMIZE PLANT POWER FACTOR $18,551 $40,582 Not Implemented
IC0197 # 01 Y:2017 01 2017 OPTIMIZE PLANT POWER FACTOR $90,126 $26,155 Implemented
OK0978 # 10 Y:2017 10 2017 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $19,215 $0 Not Implemented
OK0974 # 01 Y:2017 01 2017 OPTIMIZE PLANT POWER FACTOR $12,407 $15,373 Not Implemented