IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

224

matching recommendations
Reset
ARC 2.3 Electrical Power
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WI0267 # 07 Y:1996 07 1996 SCHEDULE ROUTINE MAINTENANCE DURING NON-OPERATING PERIODS $4,867 $0 n/a
GT0586 # 07 Y:1996 07 1996 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,060 $0 Not Implemented
UD0491 # 02 Y:1996 02 1996 OPTIMIZE PLANT POWER FACTOR $3,570 $1,000 Implemented
UD0490 # 03 Y:1996 03 1996 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,080 $100 Not Implemented
OR0262 # 05 Y:1996 05 1996 OPTIMIZE PLANT POWER FACTOR $3,101 $6,600 Not Implemented
OR0263 # 05 Y:1996 05 1996 OPTIMIZE PLANT POWER FACTOR $3,319 $9,400 Not Implemented
AM0275 # 03 Y:1996 03 1996 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,820 $0 Implemented
AM0275 # 01 Y:1996 01 1996 OPTIMIZE PLANT POWER FACTOR $19,150 $10,000 Implemented
GT0585 # 01 Y:1996 01 1996 USE POWER DURING OFF-PEAK PERIODS $10,089 $0 Implemented
GT0585 # 02 Y:1996 02 1996 OPTIMIZE PLANT POWER FACTOR $33,556 $59,500 Implemented
SD0149 # 03 Y:1996 03 1996 OPTIMIZE PLANT POWER FACTOR $3,817 $1,616 Not Implemented
UM0055 # 01 Y:1996 01 1996 OPTIMIZE PLANT POWER FACTOR $5,129 $17,603 Not Implemented
NC0081 # 08 Y:1996 08 1996 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $7,816 $0 Not Implemented
NV0055 # 02 Y:1996 02 1996 USE POWER DURING OFF-PEAK PERIODS $3,340 $0 Not Implemented
ME0185 # 04 Y:1996 04 1996 OPTIMIZE PLANT POWER FACTOR $4,144 $5,290 Implemented
CO0363 # 01 Y:1996 01 1996 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $21,800 $14,040 Not Implemented
UD0489 # 04 Y:1996 04 1996 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $488 $100 Implemented
IA0142 # 01 Y:1996 01 1996 USE DEMAND CONTROLLER OR LOAD SHEDDER $2,323 $0 Not Implemented
UD0489 # 01 Y:1996 01 1996 OPTIMIZE PLANT POWER FACTOR $2,203 $3,000 Not Implemented
WI0265 # 11 Y:1996 11 1996 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $500 $2,000 Not Implemented
SF0088 # 06 Y:1996 06 1996 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $3,454 $1,544 Not Implemented
WI0265 # 10 Y:1996 10 1996 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION $718 $0 Not Implemented
ND0240 # 07 Y:1996 07 1996 OPTIMIZE PLANT POWER FACTOR $7,294 $12,852 Implemented
SF0088 # 07 Y:1996 07 1996 OPTIMIZE PLANT POWER FACTOR $1,611 $2,106 Not Implemented
AM0274 # 01 Y:1996 01 1996 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION $18,652 $0 Not Implemented