Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
6,720
matching recommendationsARC | 4 | DIRECT PRODUCTIVITY ENHANCEMENTS |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0196 # 06 Y:1998 | 06 | 1998 | ELIMINATE/REDUCE REDUNDANT INSPECTIONS | $30,000 | $900 | Implemented |
WV0146 # 13 Y:1998 | 13 | 1998 | CLEAR AND RENT EXISTING SPACE | $57,240 | $16,800 | Not Implemented |
AR0141 # 08 Y:1998 | 08 | 1998 | REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | $50,674 | $88,000 | Not Implemented |
DS0120 # 05 Y:1998 | 05 | 1998 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $5,525 | $1,350 | Not Implemented |
UM0124 # 07 Y:1998 | 07 | 1998 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $158,133 | $30,000 | Implemented |
AS0231 # 10 Y:1998 | 10 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $6,919 | $9,000 | Not Implemented |
AS0231 # 09 Y:1998 | 09 | 1998 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $12,854 | $450 | Implemented |
SD0206 # 07 Y:1998 | 07 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $6,426 | $1,275 | Implemented |
SD0206 # 08 Y:1998 | 08 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $157,414 | $12,000 | Implemented |
SD0204 # 06 Y:1998 | 06 | 1998 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $4,891 | $3,300 | Not Implemented |
SD0204 # 05 Y:1998 | 05 | 1998 | INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM | $7,932 | $0 | Implemented |
UM0123 # 07 Y:1998 | 07 | 1998 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $5,200 | $100 | Not Implemented |
UM0123 # 08 Y:1998 | 08 | 1998 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $4,161 | $200 | Not Implemented |
MO0233 # 01 Y:1998 | 01 | 1998 | INSTALL EQUIPMENT TO MOVE PRODUCT | $42,310 | $87,250 | Not Implemented |
MO0233 # 02 Y:1998 | 02 | 1998 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $1,376 | $4,000 | Implemented |
AS0230 # 08 Y:1998 | 08 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $158,264 | $128,600 | Not Implemented |
NV0105 # 10 Y:1998 | 10 | 1998 | USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES | $52,000 | $14,200 | Implemented |
OD0112 # 07 Y:1998 | 07 | 1998 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $10,920 | $550 | Not Implemented |
UL0196 # 02 Y:1998 | 02 | 1998 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $10,845 | $13,500 | Not Implemented |
UL0196 # 04 Y:1998 | 04 | 1998 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $100,000 | $10,000 | Not Implemented |
SD0205 # 07 Y:1998 | 07 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $336,172 | $311,000 | Not Implemented |
MO0232 # 01 Y:1998 | 01 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $12,992 | $6,071 | Implemented |
SD0205 # 08 Y:1998 | 08 | 1998 | MOVE PRODUCT USING MECHANICAL MEANS | $19,800 | $8,000 | Not Implemented |
SD0205 # 09 Y:1998 | 09 | 1998 | MOVE PRODUCT USING MECHANICAL MEANS | $14,850 | $1,200 | Not Implemented |
OR0321 # 05 Y:1998 | 05 | 1998 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $2,590 | $15,000 | Not Implemented |