IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

58

matching recommendations
Reset
ARC 2.26 COOLING
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0754 # 09 Y:2007 09 2007 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE $8,086 $0 Implemented
OK0753 # 07 Y:2007 07 2007 USE COOLING TOWER WATER INSTEAD OF REFRIGERATION $3,437 $13,500 Not Implemented
WV0366 # 15 Y:2007 15 2007 UTILIZE A LESS EXPENSIVE COOLING METHOD $751 $1,641 Not Implemented
WV0366 # 12 Y:2007 12 2007 USE COOLING TOWER WATER INSTEAD OF REFRIGERATION $1,770 $5,600 Not Implemented
MA0624 # 04 Y:2007 04 2007 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE $14,298 $11,500 Implemented
UA0011 # 07 Y:2007 07 2007 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE $1,174 $0 Not Implemented
UD0767 # 06 Y:2007 06 2007 USE COOLING TOWER WATER INSTEAD OF REFRIGERATION $2,922 $5,000 Not Implemented
BD0332 # 07 Y:2007 07 2007 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE $4,182 $2 Not Implemented
OK0752 # 09 Y:2007 09 2007 USE COOLING TOWER WATER INSTEAD OF REFRIGERATION $20,273 $2,500 Not Implemented
WV0364 # 13 Y:2007 13 2007 UTILIZE A LESS EXPENSIVE COOLING METHOD $1,174 $2,445 Not Implemented
LE0262 # 03 Y:2007 03 2007 UTILIZE A LESS EXPENSIVE COOLING METHOD $173,079 $300,000 Not Implemented
OK0750 # 04 Y:2007 04 2007 SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS $8,272 $16,000 Not Implemented
MI0155 # 07 Y:2007 07 2007 USE EXCESS COLD PROCESS FLUID FOR INDUSTRIAL COOLING NEEDS $7,524 $7,800 Not Implemented
MI0155 # 01 Y:2007 01 2007 UTILIZE A LESS EXPENSIVE COOLING METHOD $66,401 $120,000 Not Implemented
LE0259 # 05 Y:2007 05 2007 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE $1,811 $200 Implemented
UA0007 # 14 Y:2007 14 2007 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE $768 $0 Not Implemented
UA0007 # 11 Y:2007 11 2007 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $2,335 $7,017 Not Implemented
MI0154 # 01 Y:2007 01 2007 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $99,787 $131,000 Not Implemented
MI0153 # 01 Y:2007 01 2007 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $342,569 $290,000 Not Implemented
UA0005 # 12 Y:2007 12 2007 USE EXCESS COLD PROCESS FLUID FOR INDUSTRIAL COOLING NEEDS $34,728 $1,615 Not Implemented
DL0002 # 03 Y:2007 03 2007 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $19,418 $73,950 Not Implemented
WV0360 # 08 Y:2007 08 2007 UTILIZE A LESS EXPENSIVE COOLING METHOD $2,676 $3,700 Implemented
MA0619 # 05 Y:2007 05 2007 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $14,883 $5,300 Not Implemented
UD0763 # 05 Y:2007 05 2007 USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE $2,275 $0 Not Implemented
LE0254 # 02 Y:2007 02 2007 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $67,570 $67,000 Not Implemented