IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

215

matching recommendations
Reset
ARC 2.3 Electrical Power
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SF0244 # 14 Y:2002 14 2002 OPTIMIZE PLANT POWER FACTOR $2,389 $3,651 Not Implemented
SF0244 # 13 Y:2002 13 2002 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $8,739 $0 Not Implemented
NC0248 # 02 Y:2002 02 2002 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $6,087 $0 Not Implemented
SF0243 # 11 Y:2002 11 2002 USE POWER DURING OFF-PEAK PERIODS $3,383 $0 Not Implemented
LE0146 # 01 Y:2002 01 2002 USE DEMAND CONTROLLER OR LOAD SHEDDER $10,029 $3,500 Not Implemented
IA0299 # 05 Y:2002 05 2002 OPTIMIZE PLANT POWER FACTOR $2,000 $2,694 Not Implemented
GT0741 # 07 Y:2002 07 2002 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT $674,846 $2,070,000 Not Implemented
SD0307 # 01 Y:2002 01 2002 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT $115,174 $476,400 Not Implemented
NC0250 # 01 Y:2002 01 2002 MAKE ICE DURING OFF PEAK HOURS FOR COOLING $13,524 $16,000 n/a
UD0655 # 03 Y:2002 03 2002 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $8,888 $0 Not Implemented
WV0251 # 05 Y:2002 05 2002 USE DEMAND CONTROLLER OR LOAD SHEDDER $13,680 $3,000 Not Implemented
OK0643 # 02 Y:2002 02 2002 OPTIMIZE PLANT POWER FACTOR $2,012 $3,430 Not Implemented
SU0140 # 01 Y:2002 01 2002 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT $593,735 $5,128,500 Not Implemented
MS0214 # 02 Y:2002 02 2002 USE DEMAND CONTROLLER OR LOAD SHEDDER $6,371 $11,500 Implemented
CO0511 # 02 Y:2002 02 2002 OPTIMIZE PLANT POWER FACTOR $10,160 $14,010 Not Implemented
NC0245 # 03 Y:2002 03 2002 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $5,574 $0 Not Implemented
CO0511 # 06 Y:2002 06 2002 USE DEMAND CONTROLLER OR LOAD SHEDDER $2,290 $1,200 Not Implemented
NC0245 # 01 Y:2002 01 2002 REPLACE ELECTRIC MOTORS WITH BACK PRESSURE STEAM TURBINES AND USE EXHAUST STEAM FOR PROCESS HEAT $142,297 $262,500 Not Implemented
UU0027 # 04 Y:2002 04 2002 OPTIMIZE PLANT POWER FACTOR $6,600 $4,500 Implemented
UD0653 # 07 Y:2002 07 2002 OPTIMIZE PLANT POWER FACTOR $1,512 $1,125 Not Implemented
LE0143 # 01 Y:2002 01 2002 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $4,545 $2,500 Not Implemented
MA0520 # 01 Y:2002 01 2002 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,609 $0 Not Implemented
MA0519 # 02 Y:2002 02 2002 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $17,181 $2,500 Not Implemented
LE0142 # 02 Y:2002 02 2002 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $18,173 $10,000 Not Implemented
CO0509 # 01 Y:2002 01 2002 USE DEMAND CONTROLLER OR LOAD SHEDDER $2,920 $8,000 Not Implemented