IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

22

matching recommendations
Reset
ARC 2.3 Electrical Power
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SD0422 # 01 Y:2009 01 2009 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $31,588 $0 Implemented
SD0422 # 02 Y:2009 02 2009 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $5,480 $0 Implemented
GT0870 # 01 Y:2009 01 2009 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $625 $0 Implemented
UD0806 # 01 Y:2009 01 2009 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION $169,364 $0 Implemented
DL0043 # 07 Y:2009 07 2009 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,060 $0 Implemented
LE0292 # 04 Y:2009 04 2009 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $4,921 $3,000 Implemented
IA0443 # 08 Y:2009 08 2009 OPTIMIZE PLANT POWER FACTOR $4,398 $4,659 Implemented
LE0291 # 03 Y:2009 03 2009 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $15,557 $2,500 Implemented
NC0393 # 02 Y:2009 02 2009 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $31,650 $1,000 Implemented
MS0342 # 02 Y:2009 02 2009 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $8,753 $0 Implemented
LE0288 # 03 Y:2009 03 2009 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $6,851 $2,500 Implemented
WV0390 # 08 Y:2009 08 2009 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $10,650 $0 Implemented
WV0390 # 03 Y:2009 03 2009 OPTIMIZE PLANT POWER FACTOR $20,264 $4,490 Implemented
BD0357 # 10 Y:2009 10 2009 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,905 $0 Implemented
UA0035 # 08 Y:2009 08 2009 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $129,337 $0 Implemented
DL0033 # 08 Y:2009 08 2009 USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS $6,433 $26,980 Implemented
SU0280 # 11 Y:2009 11 2009 OPTIMIZE PLANT POWER FACTOR $2,725 $7,949 Implemented
UD0793 # 04 Y:2009 04 2009 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION $3,855 $0 Implemented
SU0278 # 10 Y:2009 10 2009 OPTIMIZE PLANT POWER FACTOR $7,344 $28,458 Implemented
LE0283 # 02 Y:2009 02 2009 REPLACE DC EQUIPMENT WITH AC EQUIPMENT $46,426 $38,000 Implemented
MA0643 # 04 Y:2009 04 2009 OPTIMIZE PLANT POWER FACTOR $6,439 $12,500 Implemented
SU0274 # 11 Y:2009 11 2009 OPTIMIZE PLANT POWER FACTOR $1,192 $7,749 Implemented