IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,290

matching recommendations
Reset
ARC 4.1 MANUFACTURING ENHANCEMENTS
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0386 # 01 Y:2001 01 2001 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $11,500 $10,500 Not Implemented
SU0102 # 02 Y:2001 02 2001 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS $4,867 $234 Implemented
SD0269 # 06 Y:2001 06 2001 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $158,400 $2,500 Implemented
WV0209 # 14 Y:2001 14 2001 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS $34,833 $17,500 Not Implemented
OK0605 # 07 Y:2000 07 2000 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $5,473,600 $4,750,000 Not Implemented
OR0387 # 03 Y:2001 03 2001 INSTALL REFRIGERATION SYSTEM TO COOL PRODUCT $324,800 $138,000 Not Implemented
OR0387 # 01 Y:2001 01 2001 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $176,000 $5,000 Implemented
OR0387 # 02 Y:2001 02 2001 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $440,800 $128,700 Implemented
SF0210 # 01 Y:2001 01 2001 REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL $11,594 $14,640 Not Implemented
WV0208 # 10 Y:2001 10 2001 ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS $2,000 $800 Implemented
AM0387 # 01 Y:2001 01 2001 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $13,300 $45,140 Implemented
SD0262 # 11 Y:2001 11 2001 INSTALL CONTINUOUS LUBRICATION EQUIPMENT $47,470 $72,000 Not Implemented
SD0262 # 05 Y:2001 05 2001 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $38,254 $1,700 Not Implemented
SD0262 # 10 Y:2001 10 2001 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $13,222 $4,800 Not Implemented
AM0385 # 01 Y:2001 01 2001 ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS $303,000 $0 Not Implemented
MA0481 # 01 Y:2001 01 2001 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $17,820 $30,000 Implemented
BD0177 # 07 Y:2001 07 2001 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $31,899 $40,000 Not Implemented
BD0177 # 08 Y:2001 08 2001 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $27,022 $30,000 Not Implemented
BD0177 # 09 Y:2001 09 2001 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $3,497 $10,000 Not Implemented
CO0478 # 09 Y:2000 09 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $6,350 $12,000 Implemented
CO0479 # 06 Y:2000 06 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $179,700 $0 Not Implemented
GT0705 # 08 Y:2000 08 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $120,000 $700,000 Not Implemented
OK0606 # 01 Y:2000 01 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $59,500 $115,187 Not Implemented
OK0607 # 02 Y:2000 02 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $43,000 $70,000 Not Implemented
UM0176 # 04 Y:2000 04 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $127,531 $162,750 Not Implemented