IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

159

matching recommendations
Reset
ARC 2.3 Electrical Power
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UK1507 # 01 Y:2015 01 2015 OPTIMIZE PLANT POWER FACTOR $1,822 $2,818 Not Implemented
OK0921 # 02 Y:2015 02 2015 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $12,026 $832 Not Implemented
NC0548 # 02 Y:2015 02 2015 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $13,922 $5,000 Not Implemented
UD0933 # 15 Y:2015 15 2015 OPTIMIZE PLANT POWER FACTOR $4,834 $35,000 Implemented
BS0059 # 01 Y:2015 01 2015 OPTIMIZE PLANT POWER FACTOR $12,761 $18,045 Implemented
NC0547 # 13 Y:2015 13 2015 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $675 $200 Implemented
MA0749 # 04 Y:2015 04 2015 OPTIMIZE PLANT POWER FACTOR $10,366 $25,300 Not Implemented
OK0922 # 08 Y:2015 08 2015 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,542 $780 Not Implemented
OK0922 # 04 Y:2015 04 2015 OPTIMIZE PLANT POWER FACTOR $37,221 $46,451 Not Implemented
IP0043 # 04 Y:2015 04 2015 OPTIMIZE PLANT POWER FACTOR $5,219 $5,000 Not Implemented
UD0931 # 01 Y:2015 01 2015 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $108,029 $0 Not Implemented
SD0512 # 02 Y:2015 02 2015 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $39,697 $25,608 Implemented
UA0143 # 04 Y:2015 04 2015 OPTIMIZE PLANT POWER FACTOR $1,140 $2,140 Not Implemented
MI0282 # 01 Y:2015 01 2015 USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS $23,744 $1,120 Not Implemented
OK0920 # 11 Y:2015 11 2015 OPTIMIZE PLANT POWER FACTOR $3,157 $20,000 Not Implemented
BD0465 # 02 Y:2015 02 2015 MAKE ICE DURING OFF PEAK HOURS FOR COOLING $11,490 $62,000 Implemented
OR0650 # 05 Y:2015 05 2015 HEAT WATER DURING OFF-PEAK PERIODS AND STORE FOR LATER USE $1,291 $4,404 Implemented
WV0510 # 05 Y:2015 05 2015 OPTIMIZE PLANT POWER FACTOR $9,408 $24,300 Not Implemented
OK0915 # 14 Y:2015 14 2015 OPTIMIZE PLANT POWER FACTOR $9,371 $14,014 Not Implemented
SF0468 # 02 Y:2015 02 2015 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $15,328 $0 Not Implemented
MZ0185 # 01 Y:2015 01 2015 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT $444,193 $2,686,745 Not Implemented
MA0747 # 03 Y:2015 03 2015 OPTIMIZE PLANT POWER FACTOR $28,243 $56,115 Not Implemented
SD0511 # 02 Y:2015 02 2015 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $9,418 $1,750 Not Implemented
BD0464 # 05 Y:2015 05 2015 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $3,866 $20 Not Implemented
MI0279 # 11 Y:2015 11 2015 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,317 $3,280 Not Implemented