Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

6,856

matching recommendations
Reset
ARC 2.3 Electrical Power
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AM0640 # 03 Y:2013 03 2013 OPTIMIZE PLANT POWER FACTOR $18,322 $28,020 Not Implemented
UD0881 # 16 Y:2013 16 2013 BURN FOSSIL FUEL TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR AND USE STEAM EXHAUST FOR HEAT $24,715 $101,000 Not Implemented
WV0469 # 01 Y:2013 01 2013 OPTIMIZE PLANT POWER FACTOR $21,317 $6,300 Not Implemented
WV0469 # 05 Y:2013 05 2013 USE DEMAND CONTROLLER OR LOAD SHEDDER $6,853 $5,700 Not Implemented
UM0421 # 01 Y:2013 01 2013 USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST $75,276 $110,000 Not Implemented
OK0851 # 02 Y:2013 02 2013 OPTIMIZE PLANT POWER FACTOR $6,232 $14,940 Not Implemented
UD0880 # 01 Y:2013 01 2013 USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS $37,553 $100,000 Not Implemented
AM0639 # 05 Y:2013 05 2013 OPTIMIZE PLANT POWER FACTOR $5,960 $13,780 Not Implemented
BD0426 # 03 Y:2013 03 2013 USE POWER DURING OFF-PEAK PERIODS $14,106 $8,320 Not Implemented
BD0426 # 06 Y:2013 06 2013 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,416 $40 Not Implemented
WV0468 # 03 Y:2013 03 2013 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $5,882 $2,000 Not Implemented
SD0470 # 05 Y:2013 05 2013 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $4,160 $14,000 Not Implemented
AM0638 # 03 Y:2013 03 2013 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,400 $0 Not Implemented
IP0011 # 08 Y:2013 08 2013 OPTIMIZE PLANT POWER FACTOR $14,000 $9,864 Not Implemented
OR0602 # 06 Y:2013 06 2013 OPTIMIZE PLANT POWER FACTOR $3,822 $9,150 Implemented
TT0106 # 01 Y:2013 01 2013 OPTIMIZE PLANT POWER FACTOR $8,613 $37,637 Not Implemented
OK0853 # 09 Y:2013 09 2013 OPTIMIZE PLANT POWER FACTOR $3,767 $7,526 Not Implemented
MI0238 # 03 Y:2013 03 2013 REPLACE DC EQUIPMENT WITH AC EQUIPMENT $10,510 $12,640 Not Implemented
SD0468 # 03 Y:2013 03 2013 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $4,278 $1,600 Implemented
UD0878 # 01 Y:2013 01 2013 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $8,520 $0 Implemented
OK0850 # 11 Y:2013 11 2013 OPTIMIZE PLANT POWER FACTOR $2,693 $11,638 Not Implemented
OK0847 # 06 Y:2013 06 2013 OPTIMIZE PLANT POWER FACTOR $12,719 $11,540 Not Implemented
LE0362 # 04 Y:2013 04 2013 USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR $41,942 $191,591 Not Implemented
IP0010 # 13 Y:2013 13 2013 OPTIMIZE PLANT POWER FACTOR $2,850 $8,526 Implemented
LE0362 # 05 Y:2013 05 2013 OPTIMIZE PLANT POWER FACTOR $86,433 $302,515 Not Implemented