IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

76

matching recommendations
Reset
ARC 2.3 Electrical Power
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OD0105 # 01 Y:1998 01 1998 BURN WASTE TO PRODUCE STEAM TO DRIVE A STEAM TURBINE GENERATOR SET AND USE STEAM EXHAUST FOR HEAT $56,890 $175,200 Implemented
GT0655 # 01 Y:1998 01 1998 OPTIMIZE PLANT POWER FACTOR $5,800 $5,000 Implemented
OK0561 # 01 Y:1998 01 1998 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION $2,306 $5,000 Implemented
CO0429 # 01 Y:1998 01 1998 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $840 $1,000 Implemented
AM0334 # 01 Y:1998 01 1998 OPTIMIZE PLANT POWER FACTOR $18,200 $22,300 Implemented
UL0206 # 01 Y:1998 01 1998 OPTIMIZE PLANT POWER FACTOR $67,516 $0 Implemented
MS0123 # 06 Y:1998 06 1998 OPTIMIZE PLANT POWER FACTOR $11,310 $10,800 Implemented
MS0119 # 04 Y:1998 04 1998 USE DEMAND CONTROLLER OR LOAD SHEDDER $32,240 $31,500 Implemented
MS0122 # 02 Y:1998 02 1998 OPTIMIZE PLANT POWER FACTOR $2,247 $4,950 Implemented
OR0332 # 05 Y:1998 05 1998 OPTIMIZE PLANT POWER FACTOR $0 $54,400 Implemented
MA0427 # 02 Y:1998 02 1998 OPTIMIZE PLANT POWER FACTOR $5,715 $7,055 Implemented
NV0118 # 01 Y:1998 01 1998 OPTIMIZE PLANT POWER FACTOR $2,663 $3,333 Implemented
GT0646 # 04 Y:1998 04 1998 USE DEMAND CONTROLLER OR LOAD SHEDDER $2,020 $2,700 Implemented
GT0645 # 01 Y:1998 01 1998 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $20,559 $10,000 Implemented
OK0557 # 02 Y:1998 02 1998 USE POWER DURING OFF-PEAK PERIODS $15,633 $0 Implemented
NV0115 # 01 Y:1998 01 1998 OPTIMIZE PLANT POWER FACTOR $1,772 $2,333 Implemented
NC0149 # 02 Y:1998 02 1998 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,438 $100 Implemented
KU0503 # 01 Y:1998 01 1998 OPTIMIZE PLANT POWER FACTOR $24,460 $29,380 Implemented
KU0502 # 01 Y:1998 01 1998 OPTIMIZE PLANT POWER FACTOR $7,420 $12,600 Implemented
NV0113 # 03 Y:1998 03 1998 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT $278,123 $520,000 Implemented
WI0333 # 08 Y:1998 08 1998 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $847 $400 Implemented
DS0124 # 03 Y:1998 03 1998 OPTIMIZE PLANT POWER FACTOR $30,549 $25,900 Implemented
GT0640 # 01 Y:1998 01 1998 OPTIMIZE PLANT POWER FACTOR $28,530 $45,720 Implemented
MS0118 # 02 Y:1998 02 1998 OPTIMIZE PLANT POWER FACTOR $818 $390 Implemented
UL0201 # 01 Y:1998 01 1998 OPTIMIZE PLANT POWER FACTOR $958 $3,132 Implemented