Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

220

matching recommendations
Reset
ARC 2.3 Electrical Power
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD0664 # 01 Y:2003 01 2003 USE DEMAND CONTROLLER OR LOAD SHEDDER $115,000 $1,000 Not Implemented
UD0664 # 05 Y:2003 05 2003 USE DEMAND CONTROLLER OR LOAD SHEDDER $16,536 $2,600 Not Implemented
OK0657 # 02 Y:2003 02 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,220 $25 Implemented
SF0255 # 09 Y:2003 09 2003 OPTIMIZE PLANT POWER FACTOR $678 $1,749 Not Implemented
CO0521 # 06 Y:2003 06 2003 USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST $48,290 $175,000 Not Implemented
MA0529 # 01 Y:2003 01 2003 USE STEAM PRESSURE REDUCTION TO GENERATE POWER $132,710 $407,000 n/a
GT0752 # 09 Y:2003 09 2003 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT $435,100 $2,070,000 Not Implemented
SU0155 # 02 Y:2003 02 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $17,787 $1,200 Implemented
UM0228 # 04 Y:2003 04 2003 OPTIMIZE PLANT POWER FACTOR $1,901 $654 Not Implemented
SF0254 # 06 Y:2003 06 2003 OPTIMIZE PLANT POWER FACTOR $7,343 $11,038 Not Implemented
UF0316 # 11 Y:2003 11 2003 OPTIMIZE PLANT POWER FACTOR $15,362 $9,000 Not Implemented
LL0156 # 02 Y:2003 02 2003 USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR $918,298 $3,111,056 Not Implemented
UD0663 # 06 Y:2003 06 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $24,572 $0 Not Implemented
UU0039 # 09 Y:2003 09 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $7,608 $0 Implemented
WI0438 # 01 Y:2003 01 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $9,005 $15,000 Implemented
UU0039 # 08 Y:2003 08 2003 OPTIMIZE PLANT POWER FACTOR $695 $695 Implemented
AM0431 # 02 Y:2003 02 2003 OPTIMIZE PLANT POWER FACTOR $5,030 $11,900 Not Implemented
UD0662 # 05 Y:2003 05 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,817 $0 Not Implemented
LL0157 # 04 Y:2003 04 2003 OPTIMIZE PLANT POWER FACTOR $3,129 $17,080 Not Implemented
UM0226 # 07 Y:2003 07 2003 OPTIMIZE PLANT POWER FACTOR $2,055 $1,560 Not Implemented
CO0522 # 03 Y:2003 03 2003 USE DEMAND CONTROLLER OR LOAD SHEDDER $4,300 $840 Not Implemented
IA0311 # 09 Y:2003 09 2003 OPTIMIZE PLANT POWER FACTOR $20,493 $13,500 Implemented
UD0661 # 04 Y:2003 04 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $5,298 $0 Not Implemented
UD0661 # 08 Y:2003 08 2003 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,620 $0 Not Implemented
BD0225 # 14 Y:2003 14 2003 USE POWER DURING OFF-PEAK PERIODS $3,393 $4,000 Not Implemented