IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

31

matching recommendations
Reset
ARC 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
GT0703 # 06 Y:2000 06 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $10,968 $0 Not Implemented
BD0175 # 03 Y:2000 03 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,116 $0 Not Implemented
TN0696 # 06 Y:2000 06 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $35,400 $18,900 Implemented
AM0379 # 02 Y:2000 02 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $13,850 $0 Implemented
WI0382 # 02 Y:2000 02 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $850 $2,000 Not Implemented
WI0381 # 02 Y:2000 02 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $4,183 $4,000 Implemented
TN0693 # 06 Y:2000 06 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $8,508 $18,900 Not Implemented
SD0258 # 04 Y:2000 04 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $3,957 $0 Not Implemented
TN0692 # 07 Y:2000 07 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $3,600 $900 Implemented
SD0257 # 08 Y:2000 08 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $11,760 $0 Implemented
NC0193 # 05 Y:2000 05 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $35,491 $500 Not Implemented
AR0185 # 02 Y:2000 02 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $6,930 $0 Not Implemented
ND0353 # 08 Y:2000 08 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $20,782 $25,000 Implemented
UD0600 # 03 Y:2000 03 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $3,810 $0 Not Implemented
MO0279 # 04 Y:2000 04 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $8,280 $4,500 Not Implemented
GT0689 # 01 Y:2000 01 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $32,450 $0 n/a
WI0376 # 06 Y:2000 06 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,719 $4,000 n/a
WI0376 # 03 Y:2000 03 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $3,131 $0 n/a
HO0230 # 01 Y:2000 01 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $15,545 $0 Not Implemented
KU0539 # 04 Y:2000 04 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,800 $0 Not Implemented
GT0687 # 02 Y:2000 02 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $33,596 $0 Not Implemented
WI0372 # 06 Y:2000 06 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,632 $0 Not Implemented
WI0372 # 05 Y:2000 05 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,804 $2,000 Not Implemented
SD0242 # 03 Y:2000 03 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $4,568 $0 Not Implemented
GT0685 # 01 Y:2000 01 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $5,280 $0 Implemented